Natural Gas Pipeline Company Of America

Seventh Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 04/18/2008, Docket: RP08-319-000, Status: Effective

Original Sheet No. 90 Original Sheet No. 90 : Pending

 

 

RATE SCHEDULE FRSS

------------------

 

(c) Natural shall not be required, except to the extent it

has accepted confirmed nominations allowing authorized overrun, to:

(1) withdraw hereunder on any day gas requested in excess of

Shipper's Maximum Daily Withdrawal Quantity (WQ) or in excess of

Shipper's Maximum Seasonal Withdrawal Quantity (MSWQ); (2) accept on

any day gas tendered for injection hereunder in excess of Shipper's

Maximum Daily Injection Quantity (IQ); or (3) deliver gas at Delivery

Points or accept gas at Receipt Points on a basis which is not

consistent with Section 7 of this Rate Schedule FRSS and the related

General Terms and Conditions of this Tariff. The terms "IQ", "WQ"

and "MSWQ" are defined in Section 5 of this Rate Schedule FRSS.

Service hereunder shall be firm within WQ, MSWQ and IQ. Gas may not

be injected hereunder during the Withdrawal Period, nor may gas be

withdrawn during the Injection Period, as those terms are defined in

Section 5 of this Rate Schedule FRSS. Volumes of gas withdrawn

during the Withdrawal Period must be replaced by equivalent volumes

of gas injected by the end of the Injection Period.

 

(d) The service provided under this Rate Schedule FRSS shall

be performed under Part 284 of the Commission's Regulations. Shipper

shall only take or tender gas under this Rate Schedule FRSS to the

extent such service would qualify under the applicable statutes,

regulations, Commission orders and the blanket certificate

authorizing service by Natural under this Rate Schedule FRSS. For

service under Subpart B of Part 284 of the Commission's Regulations,

Shipper shall provide to Natural appropriate certification, including

sufficient information in order for Natural to verify that the

service qualifies under Subpart B of Part 284 of the Regulations.

Where required by the Commission's Regulations, Shipper shall (prior

to using service under a FRSS Agreement) cause the intrastate

pipeline or local distribution company on whose behalf the service

will be provided to submit the necessary certification to Natural.

 

(e) As more fully set out in the General Terms and Conditions

of this Tariff, Natural is not providing a gas supply service under

this Rate Schedule FRSS. This service will be provided through the

management by Natural of its cushion gas and storage operations at

all of its storage fields and related facilities.

 

(f) Allocation of capacity, curtailment, and priorities of

service for the purposes of scheduling and curtailment shall all be

governed by Section 7 of this Rate Schedule FRSS and the General

Terms and Conditions of this Tariff.