Natural Gas Pipeline Company Of America

Seventh Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 04/18/2008, Docket: RP08-319-000, Status: Effective

Original Sheet No. 76 Original Sheet No. 76 : Pending

 

 

RATE SCHEDULE FTS

-----------------

 

associated with more than one NSS Agreement or Third Party Storage

Point; provided, however, that under a predetermination allocation

agreement pursuant to Section 11 of the General Terms and Conditions

of this Tariff, a Shipper or point operator can designate a linkage

between an FTS Agreement and multiple NSS Agreements and Third Party

Storage Points so long as an administratively workable protocol for

linking the transportation and storage components is specified. The

designations hereunder may be changed on reasonable prior notice to

Natural.

 

(5) The NB option is available for use only in

conjunction with an NSS Agreement or comparable third party storage

agreement at a Third Party Storage Point. The NB option shall

terminate if neither of such elements is present.

 

(e) No-notice activity under an FTS-NB Agreement will be

posted to the storage point in the receipt zone where the imbalance

occurs or to the closest storage point where Shipper has adequate

storage rights to accommodate such activity, consistent with Section

5.6(c)(4) of the General Terms and Conditions of this Tariff.

 

5.4 A Shipper under Rate Schedule FTS is not obligated to

choose any of the options described in this Section 5, but may

select any one of them, any two of them or all three of them. Once

a Shipper has elected an option and so long as it remains in effect,

the Agreement for service to such Shipper may be referenced by placing

the relevant letters after FTS.

 

6. RATE

 

6.1 Shipper shall pay Natural each month for service under

this Rate Schedule FTS the sum of the following charges:

 

(a) a Reservation Charge based on Shipper's MDQ;

 

(b) a Commodity Charge for each unit of gas delivered

hereunder by Natural during the billing month;

 

(c) Gathering and Offshore Charge(s);

 

(d) all applicable types of transition cost charges; and

 

(e) any other applicable charges and penalties set out in

this Rate Schedule FTS or the General Terms and Conditions of

this Tariff.