Natural Gas Pipeline Company Of America
Seventh Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/18/2008, Docket: RP08-319-000, Status: Effective
Original Sheet No. 46 Original Sheet No. 46 : Pending
RATE SCHEDULE FFTS
------------------
(a) GAS QUANTITIES
The request shall specify in Dth the aggregate MDQ
and the MDQ for each primary point, exclusive of applicable Fuel Gas
and Gas Lost and Unaccounted For, provided that Natural shall not be
obligated to accept requests for an aggregate MDQ of less than one
hundred (100) Dth per day. If Shipper is willing to accept a lesser
MDQ than it has requested, Shipper shall also specify the minimum
acceptable MDQ. The request shall also specify the minimum and
maximum acceptable number of Available Days; the associated defined
time period(s); whether Shipper is willing to accept notification of
partial Available Days under Section 7.1(a) hereof (and any
limitations on such agreement); and whether Shipper requests that
certain days not be Available Days. The minimum and maximum number
of Available Days or other parameters as to Available Days may vary
from one defined time period to another over the term of the FFTS
Agreement and the request must specify any such variance desired by
Shipper.
(b) RECEIPT POINT(S)
The request shall specify the primary point(s) at
which Shipper desires Natural to receive gas. By utilizing the
comment section, the request may also specify a pipeline segment if
the Shipper is willing to accept any point in that segment or the
request may specify points which Shipper is willing to accept, and/or
which points Shipper is not willing to accept, within a pipeline
segment.
(c) DELIVERY POINT(S)
The request shall specify the primary point(s) at
which Shipper desires Natural to deliver gas. By utilizing the
comment section, the request may also specify a pipeline segment if
the Shipper is willing to accept any point in that segment or the
request may specify points which Shipper is willing to accept, and/or
which points Shipper is not willing to accept, within a pipeline
segment.
(d) LIMITATION OF POINT(S)
(1) A Shipper may request any number of primary
Receipt and primary Delivery Points so long as the summation of MDQs
at all primary Receipt Points and at all primary Delivery Points
equals the aggregate MDQ.