Williston Basin Interstate Pipeline Co.

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 02/01/1997, Docket: RP97-215-002, Status: Effective

First Revised Sheet No. 328A First Revised Sheet No. 328A : Effective

Superseding: Original Sheet No. 328A

GENERAL TERMS AND CONDITIONS (Continued)

 

38. FUEL REIMBURSEMENT ADJUSTMENT PROVISION (Continued)

 

August 1 of each year. The per

unit Gas Fuel Reimbursement

Surcharge Percentage-Storage

shall be determined by dividing

the per unit Gas Fuel

Reimbursement Surcharge Amount-

Storage by the projected system

annual average cost of gas

reflected in the same filing.

 

38.5.1.4.2 The per unit Electric Power Fuel

Reimbursement Surcharge Amount-

Storage shall be determined by

dividing the applicable amounts

accumulated in the Electric Power

Unrecovered Fuel Reimbursement

Account-Storage during

Transporter's deferral period,

defined as the twelve (12) month

period ending four (4) months

prior to the effective date of

Transporter's annual filing

described in Subsection 38.5.1.2,

by the sum of the contract

storage injections and

withdrawals projected by

Transporter for the twelve (12)

month effective period beginning

August 1 of each year. The per

unit Electric Power Fuel

Reimbursement Surcharge

Percentage-Storage shall be

determined by dividing the per

unit Electric Power Fuel

Reimbursement Surcharge Amount-

Storage by the projected annual

system average cost of gas

reflected in the same filing.

 

38.5.1.4.3 The sum of the per unit Gas Fuel

Reimbursement Surcharge Amount-

Storage and the per unit Electric

Power Fuel Reimbursement

Surcharge Amount-Storage as