GENERAL TERMS AND CONDITIONS (Continued)
37. TAKE-OR-PAY BUYOUT AND BUYDOWN COST RECOVERY MECHANISM
(For Filings Submitted to FERC After November 1, 1990) (Continued)
which Transporter otherwise agreed or was required to absorb. In
addition, if applicable, Transporter shall also collect by direct
billing to any such Shipper, the product of (1) the difference between
the adjusted throughput surcharge for such Shipper resulting from the
prudence challenge and the throughput surcharge billed to the Shipper,
if any, by Transporter prior to the adjustment and (2) the quantities
transported for such Shipper up through the effective date of the
adjusted throughput surcharge, plus carrying charges in accordance with
Section 154.501 of the FERC's Regulations.
In the event any Service Agreement between Transporter, under any Rate
Schedule under Transporter's canceled sales service provided under
Transporter's canceled FERC Gas Tariff, First Revised Volume No. 1,
and/or Original Volume Nos. 1-A, 1-B and 2, or its currently effective
FERC Gas Tariff, Second Revised Volume No. 1, and any person who is
subject to charges under this Subsection 37.7, is terminated or has its
term reduced for any reason, including, but not limited to, the
expiration of said agreement, cancellation and abandonment of service,
conversion of such agreement to transportation service, or a change in
corporate identity or bankruptcy, such person shall not be relieved of
its obligations under this Subsection 37.7, and Transporter may collect
amounts due by direct billing to such person.
(The rest of this sheet has been intentionally left blank.)