37. TAKE-OR-PAY BUYOUT AND BUYDOWN COST RECOVERY MECHANISM
(For Filings Submitted to FERC After November 1, 1990) (Continued)
Payments provisions of the applicable General Terms and Conditions of
Transporter's FERC Gas Tariff, Second Revised Volume No. 1.
37.7 Prudence. This section establishes Transporter's method of
recovery of buyout/buydown costs following an unsuccessful prudence
challenge before the FERC by Shipper (which term, as applicable, shall
also include, for purposes of this Subsection 37.7, a customer receiving
sales or transportation service under Transporter's canceled FERC Gas
Tariff, Volume Nos. 1, 1-A, 1-B and 2 and/or Transporter's currently
effective Second Revised Volume No. 1) or by a regulatory agency in a
state served by Shipper, consumer advocates or other organizations in a
state served by Shipper charged with representing consumers in
regulatory proceedings or by an organization of which Shipper is a
member. If such challenge occurs, Transporter shall be authorized to
collect from Shipper the full portion of the total costs to be recovered
under this Section 37, which is applicable to Shipper under
Transporter's subject filing pursuant to this Section 37, not reduced by
the portion thereof which Transporter otherwise agreed or was required
to absorb. The amounts to be collected pursuant to the immediately
preceding sentence, increased by appropriate carrying charges in
accordance with Section 154.501 of the FERC's Regulations, shall
constitute the Adjusted Full Amount. Such adjusted full amount shall be
collected from Transporter's previous sales customers served under Rate
Schedules G-1 and SGS-1 contained in Transporter's canceled FERC Gas
Tariff, First Revised Volume No. 1, in the form of an additional fixed
monthly surcharge, of the type provided for and pursuant to Subsection
37.3.1 hereof, but with the amount increased to the adjusted full
amount. Such adjusted full amount shall be collected, as applicable,
from a Shipper served under Transporter's previously effective FERC Gas
Tariff, Volume Nos. 1-A, 1-B and 2 and/or Transporter's currently
effective Second Revised Volume No. 1, in the form of an adjustment to
the applicable throughput surcharge for such Shipper which is due under
Subsection 37.3.3 hereof, which adjustment shall increase such surcharge