Williston Basin Interstate Pipeline Co.

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 08/23/2004, Docket: RP04-410-000, Status: Effective

Third Revised Sheet No. 266 Third Revised Sheet No. 266 : Effective

Superseding: Second Revised Sheet No. 266

GENERAL TERMS AND CONDITIONS (Continued)

 

17. FIRM CAPACITY RELEASE MECHANISM (Continued)

 

9. Will the releasing Shipper accept bids which are contingent from

the bidder's point of view?: [ ]Yes [ ]No

If Yes, state: Contingency End Date ______________

Contingency End Time ______________

 

State terms, if any, under which contingent bids will be

accepted: ______________________________________________

________________________________________________________

________________________________________________________

 

10. Will releasing Shipper allow Replacement Shipper to re-release

capacity?: [ ]Yes [ ]No

 

11. Primary receipt point(s) involved in the firm transportation release.

Please list on attached Exhibit A.

(i) Will the Replacement Shipper be permitted to amend the primary

receipt point(s) listed on Exhibit A?

[ ] Yes [ ] No

 

If yes, please list the points for which an amendment will be

allowed:______________________________________________________

______________________________________________________________

 

12. For Rate Schedule FTN-1 service, the receipt point information, along

with the designated priorities, that relate to the no-notice supply

sources, if any, that are in addition to storage must be provided in the

designated section of Exhibit A.

 

13. Primary delivery point(s) involved in the firm transportation or no-

notice firm transportation service release. Please list on attached

Exhibit B.

 

(i) Will the Replacement Shipper be permitted to amend the primary

delivery point(s) listed on Exhibit B?

[ ] Yes [ ] No

 

If yes, please list the points for which an amendment will be

allowed:_____________________________________________________

_____________________________________________________________

 

14. Please identify the contract path of the capacity being released on

attached Exhibit C.