GENERAL TERMS AND CONDITIONS (Continued)
4. QUALITY (Continued)
applicable quality specifications shall not be construed to eliminate,
or limit in any manner, the rights and obligations existing under any
other provisions of the Service Agreement.
4.15 Unless otherwise mutually agreed upon, the cost of any
additional gas analysis and quality control equipment, including
installation costs and any associated tax effects, which Transporter, in
its reasonable discretion, determines is required to be installed to
monitor the quality of gas received at a point(s) of receipt, shall be
borne by Point Operator. Such equipment shall be owned and maintained
by Transporter. Transporter's decision to require the installation of
the necessary equipment to protect its system integrity at a receipt
point will be exercised in a non-discriminatory manner.
5. MEASUREMENT
5.1 Measuring station: Unless otherwise agreed upon by Transporter
and the Point Operator of the receipt and/or delivery point hereunder,
Transporter shall install and maintain an orifice meter, a rotary meter,
a turbine meter or a diaphragm meter of standard make at the point(s) of
receipt and delivery, together with all mechanical or Electronic
Correcting Device (ECD) equipment required to measure accurately the gas
received, transported and delivered hereunder. Unless otherwise
mutually agreed upon, the cost of such equipment, including installation
costs and any associated tax effects, shall be borne by Point Operator.
Such equipment shall be owned and maintained by Transporter.
Transporter shall cause the chart on all gas measurement equipment to be
changed, or mechanical or electronic indices read, by either Transporter
or Point Operator (where economical) on a daily basis or at intervals no
longer than once every eight (8) days unless otherwise mutually agreed
upon; however, all gas measurement charts shall be changed, or indices
read as near as practical to the beginning of the first day of each
month.
5.1.1 Unless otherwise mutually agreed upon, the cost of any
additional measurement equipment, including installation costs
and any associated tax effects, which Transporter, in its
reasonable discretion, determines is required to be installed
shall be borne by the Point Operator. Such equipment shall be
owned and maintained by Transporter. Transporter's decision to
require the installation of the necessary measurement equipment
will be exercised in a non-discriminatory manner.