Williston Basin Interstate Pipeline Co.

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 09/01/2003, Docket: RP03-286-000, Status: Suspended

Fourth Revised Sheet No. 93 Fourth Revised Sheet No. 93 : Suspended

Superseding: Third Revised Sheet No. 93

RATE SCHEDULE IT-1

INTERRUPTIBLE TRANSPORTATION SERVICE (Continued)

 

6. FUEL AND ELECTRIC POWER REIMBURSEMENT (Continued)

 

The Total Fuel Reimbursement Percentage per dkt and Total Electric Power

Reimbursement Rate per dkt, as applicable, shall be applied to the

quantities of gas tendered to Transporter for Shipper's account at the

receipt point(s) into Transporter's gathering and/or transmission

facilities, as applicable.

 

7. CONDITIONS OF SERVICE

 

7.1 To qualify for service pursuant to this Rate Schedule, a

potential Shipper shall make a request for transportation service

pursuant to the provisions of Section 7 of the General Terms and

Conditions.

 

7.2 Shipper shall have sole responsibility for all arrangements

necessary for delivery of natural gas to Transporter at the receipt

point(s) for transportation, and for all arrangements necessary for the

receipt of gas at the delivery point(s).

 

7.3 Shipper may be required periodically to update the credit

information originally provided in the Transportation/Storage Service

Request Form.

 

 

(The rest of this sheet has been intentionally left blank.)