Williston Basin Interstate Pipeline Co.

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 06/01/1997, Docket: RP97-352-000, Status: Effective

Third Revised Sheet No. 46 Third Revised Sheet No. 46 : Effective

Superseding: Second Revised Sheet No. 46

RATE SCHEDULE FTN-1

NO-NOTICE FIRM TRANSPORTATION SERVICE (Continued)

 

2. APPLICABILITY AND CHARACTER OF SERVICE (Continued)

 

below the daily nominated and scheduled quantity of firm

transportation service provided under Rate Schedule FT-1 up to

the Maximum Daily Delivery Quantity (MDDQ) specified for that

delivery point in Exhibit A to the Service Agreement under this

Rate Schedule FTN-1, as adjusted pursuant to the Capacity

Adjustment Provision (CAP) (described in Subsection 1.47 of the

General Terms and Conditions of this Tariff). Provided,

however, that Transporter shall not be required to execute a

Service Agreement under this Rate Schedule for an MDDQ that

exceeds Shipper's MDDQ under the corresponding Rate Schedule

FT-1 Service Agreement.

 

2.2 It is recognized that the availability of gas supply is

critical to the service to be provided hereunder. Therefore,

to obtain service hereunder, Shipper must also contract for

firm contract storage service under Rate Schedule FS-1

specifying a Maximum Storage Deliverability Quantity (MSDQ)

such that the ratio of Shipper's Rate Schedule FS-1 MSDQ to

Shipper's Rate Schedule FTN-1 MDDQ is at least equivalent to

the ratio of the total Rate Schedule FS-1 MSDQ available when

Transporter's Tariff became effective to the total sales

service MDQ used to initially allocate such total Rate Schedule

FS-1 MSDQ in accordance with Subsection 1.4 of Rate Schedule

FS-1.

 

2.3 For no-notice service above the daily nominated and scheduled

quantity of firm transportation service.

 

2.3.1 To the extent that the MDDQ specified for service under

Rate Schedule FTN-1 exceeds Shipper's Rate Schedule FS-

1 MSDQ, Shipper shall be required to have in place a

supply contract(s) which is capable of making available

an amount of natural gas equal to the amount of the

difference between Shipper's Rate Schedule FTN-1 MDDQ

and Shipper's Rate Schedule FS-1 MSDQ. The supply

contract(s) must specify a receipt point(s) on

Transporter's system within Shipper's existing contract

path specified in the Rate Schedule FT-1 Service

Agreement.

 

2.3.1.1 The Service Agreement shall specify such

supply contract(s), the applicable receipt