Sg Resources Mississippi, L.L.C
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/01/2008, Docket: RP08-184-001, Status: Effective
Substitute Original Sheet No. 49 Substitute Original Sheet No. 49 : Pending
IB RATE SCHEDULE
INTERRUPTIBLE BALANCING SERVICE
(Continued)
(b) The storage of Gas in amounts up to Customer's
Interruptible balancing Maximum Storage Quantity, provided that
all Firm Storage Service storage and system needs have been
satisfied; and
(c) The withdrawal from storage on any Day and
delivery of SGRM's Gas (as loan Gas) or Customer's Gas per
Customer's nomination to the Point(s) of Delivery which is the
excess of (i) the quantity of Gas delivered to Customer at any
Point(s) of Delivery per Customer's nomination(s), minus (ii) the
quantity of Gas received from Customer at any Point(s) of Receipt
per Customer's nomination(s), provided that all Firm Storage
Service nominations for withdrawal and system needs have been
satisfied, and that Customer has a quantity of Gas stored in
Interruptible Storage Inventory or available under its Maximum
Loan Quantity not less than the quantity the Customer shall have
nominated for withdrawal on such Day.
To the extent Interruptible storage capacity or Gas which is
being utilized by an Interruptible Customer hereunder is needed by
SGRM in order to satisfy SGRM's obligations to Firm Storage
Service Customers, SGRM shall require Customer to withdraw or
repay all, or any portion of, the IB Gas quantities held or loaned
by SGRM for the account of Customer, as specified by SGRM. Unless
SGRM otherwise agrees, Customer shall be required to make ratable
injections or withdrawals. If Customer fails to withdraw such IB
storage Gas, then SGRM may take, free and clear of any adverse
claims, title to such IB Storage Inventory as Customer was
instructed to withdraw. If Customer fails to inject such IB
storage Gas, then SGRM may purchase replacement Gas and Customer
shall pay SGRM the cost of the replacement Gas, which includes the
actual cost of replacement supplies and any costs or penalties
incurred by SGRM or its Customers as a result of Customer's
failure to deliver replacement Gas, plus all other costs incurred
by SGRM to secure such replacement Gas, including, but not limited
to, third-party marketing fees, transportation by third-party
pipeline companies, and all other costs for securing replacement
Gas. SGRM's notice to Customer may be given orally, but shall be
confirmed in writing via e-mail or facsimile to the Customer.
In the event that SGRM retains and takes title to any of
Customer's Gas pursuant to this Section, SGRM shall dispose of
such Gas by auction in accordance with the provisions of Section
32 of the General Terms and Conditions of this FERC Gas Tariff and
shall credit the price realized for such Gas at auction to
Customer, less SGRM's actual costs incurred in conducting the
auction.