Sg Resources Mississippi, L.L.C
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/01/2008, Docket: RP08-184-001, Status: Effective
Substitute Original Sheet No. 26 Substitute Original Sheet No. 26 : Pending
SFS RATE SCHEDULE
SECONDARY FIRM STORAGE SERVICE
(Continued)
(c) The withdrawal from storage on any Day of
Customer's Gas per Customer's nomination up to Customer's Maximum
Daily Withdrawal Quantity ("MDWQ") as stated in Customer's
executed Secondary Firm Storage Service Agreement and the delivery
of such Gas to the Point(s) of Delivery, provided that Customer
has a quantity of Gas in Customer's secondary firm Storage
Inventory not less than the quantity Customer shall have nominated
for withdrawal on such Day.
2.2 Provided that the receipt of Gas from Customer and the
injection of such Gas into storage can be accomplished by SGRM
without detriment to SGRM's facilities and/or SGRM's ability to
meet its firm obligations to other Customers, SGRM may, upon
Customer's request and after confirmation by Customer's
Transporter, schedule and inject on an Interruptible basis
quantities of Gas in excess of Customer's MDRQ at a Point of
Receipt, or at a Point of Receipt for which Customer's MDRQ is
zero, including total injections in excess of Customer's MDIQ,
provided that Customer's secondary firm Storage Inventory has not
exceeded Customer's Maximum Storage Quantity. Such excess
quantities shall be deemed to be "Excess Injection Gas."
2.3 Provided that such withdrawal of Gas from storage and
delivery of such Gas to Customer can be accomplished by SGRM
without detriment to SGRM's facilities and/or SGRM's ability to
meet its firm obligations to other Customers, SGRM may, upon
Customer's request and after confirmation by Customer's
Transporter, schedule and withdraw on an Interruptible basis
quantities of Gas in excess of Customer's MDDQ at a Point of
Delivery, or at a Point of Delivery for which Customer's MDDQ is
zero, including total withdrawals in excess of Customer's MDWQ,
provided that Customer has a quantity of Gas in Customer's
secondary firm Storage Inventory not less than the quantities
Customer shall have nominated for withdrawal on such Day. Such
excess quantities shall be deemed to be "Excess Withdrawal Gas."
2.4 To the extent secondary firm storage capacity which is
being utilized by a secondary firm Customer hereunder is needed by
SGRM in order to satisfy SGRM's obligations to Customers under
Rate Schedule FSS, SGRM shall require Customer to withdraw all, or
any portion of, Customer's secondary firm Gas quantities held in
storage by SGRM as specified by SGRM. Unless SGRM otherwise
agrees, Customer shall be required to make ratable withdrawals.
If Customer fails to withdraw such secondary firm storage Gas,
SGRM may take, free and clear of any adverse claims, title to such
secondary firm Storage Inventory as Customer was instructed to
withdraw. SGRM's notice to Customer may be given verbally, but
shall be confirmed in writing via e-mai1 or facsimile to the
Customer.
In the event that SGRM retains and takes title to any of
Customer's Gas pursuant to this Section, SGRM shall dispose of
such Gas by auction in accordance with the provisions of Section
32 of the General Terms and Conditions of this FERC Gas Tariff and
shall credit the price realized for such Gas at auction to
Customer, less SGRM's actual costs incurred in conducting the
auction.