29. FEDERAL ENERGY REGULATORY COMMISSION ANNUAL CHARGE ADJUSTMENT
PROVISION
29.1 Purpose
Section 3401 of the Omnibus Budget Reconciliation Act of 1986
provides that the Federal Energy Regulatory Commission (FERC)
establish an annual charge for each fiscal year ending
September 30, in an amount equal to costs incurred to operate
the Federal Energy Regulatory Commission for the fiscal year.
For the purpose of funding of Federal Energy Regulatory
Commission costs incurred in any fiscal year, this Section
establishes as part of Pipeline's rates an Annual Charge
Adjustment (ACA) Provision to be applicable to the Pipeline's
Rate Schedules ITS and FTS. The Pipeline does not intend to
recover any annual charges recorded in FERC Account No. 928 in
a Natural Gas Act Section 4 rate case.
29.2 Basis of the Annual Charge Adjustment
The Rate Schedules ITS and FTS specified in Section 29.1 hereof
shall include an increment for an Annual Charge Adjustment
(ACA) for Federal Energy Regulatory Commission costs. The
unit rate of such charge shall be that amount, adjusted to the
Pipeline's pressure base and heating value, if required, which
has been specified by the Federal Energy Regulatory Commission
each year. The current effective Annual Charge Adjustment is
set forth on Sheet No. 4.
29.3 Filing Procedures
The Annual Charge Adjustment Provision may be placed into
effect upon not less than 30 days notice unless, for good cause
shown, a lesser notice period is allowed by valid Commission
order.