11.5 Subject to the conditions of the Rate Schedule under which Shipper
is receiving service and the provisions of Sections 4, 8, 9, 10
and 12 herein, Shipper may nominate Quantities of Gas to be
delivered to any Point of Delivery identified in the Service
Agreement, up to the Quantity of Gas assigned to such Point of
Delivery in the Service Agreement.
(a) If the Shipper's Service Agreement has not been assigned in
whole or in part pursuant to Section 14 of these General
Terms and Conditions, the sum of the Quantities of Gas
nominated by the Shipper to any secondary firm Point(s) of
Delivery, together with the sum of the Quantities of Gas
nominated to a primary firm Point(s) of Delivery shall not
exceed the Maximum Daily Contract Quantity specified in the
Shipper's Service Agreement; provided, however, if the
Shipper utilizes two (2) or more discrete pipeline segments,
the sum of the Quantities of Gas nominated by the Shipper to
all Point(s) of Delivery may exceed the Maximum Daily
Contract Quantity specified in the Service Agreement so long
as the Quantities nominated for transportation in a pipeline
segment do not exceed the Maximum Daily Contract Quantity
applicable to such segment.
(b) If the Shipper's Service Agreement has been assigned in part
pursuant to Section 14 of these General Terms and Conditions
and has not been recalled pursuant to Section 14.1(e):
(i) the sum of the Quantities of Gas nominated by the
Replacement Shipper to any secondary firm Point(s) of
Delivery, together with the sum of the Quantities of
Gas nominated to primary firm Point(s) of Delivery,
shall not exceed the Maximum Daily Contract Quantity
in the Replacement Shipper's Service Agreement;
provided, however, if the Replacement Shipper utilizes
two (2) or more discrete KPC segments, the sum of the
Quantities of Gas nominated by the Replacement Shipper
to all Point(s) of Delivery may exceed the Maximum
Daily Contract Quantity specified in the Service
Agreement so long as the Quantities nominated