GENERAL TERMS AND CONDITIONS (Continued)
written notice to KPC. Such request may be submitted once in
any Fifteen (15) Day period.
(b) A Shipper may submit a request to change any secondary firm
Point of Receipt or to modify the Quantity of Gas assigned
to any secondary firm Point of Receipt at any time. KPC
shall tender a revised contract within one (1) Business Day
of receipt of such request.
10.9 Upon agreement by operator and KPC, multiple measuring stations
belonging to a single operator may constitute a single Point of
Receipt.
11. POINTS OF DELIVERY
11.1 A Point of Delivery shall be equipped with a Control Device(s)
(pressure and/or flow) if service at the Point of Delivery is
provided under any Firm Rate Schedule.
11.2 A Shipper may designate any Point of Delivery for Gas to be
delivered under a particular Transportation Rate Schedule. Each
Point of Delivery for firm service shall be identified in the
Service Agreement as either primary firm Point(s) of Delivery or
secondary firm Point(s) of Delivery. The sum of the Quantities of
Gas of all primary firm Point(s) of Delivery specified in the
Transportation Agreement may not exceed the firm Maximum Daily
Contract Quantity stated in the Transportation Agreement, except
that a Shipper may exceed its firm Maximum Daily Contract Quantity
at a particular point if, as a result of segmentation, such
deliveries consists of a forwardhaul(s) and a backhaul(s) to the
same point. Nominations that result in a reversal of the Capacity
Path will be considered out of the path for scheduling purposes.
Unless the Shipper specifies otherwise, the Quantity of Gas
assigned to each secondary firm Point of Delivery the Shipper
designates in a rate zone shall equal the sum of the Quantities of
Gas assigned to the primary firm Points of Delivery in the same
rate zone and downstream thereof.
11.3 Subject to the conditions of the Rate Schedule under which Shipper
is receiving service, Shipper may have multiple primary and
secondary Points of Delivery.
11.4 Upon agreement by operator and KPC, multiple measuring stations
belonging to a single operator may constitute a single Point of
Delivery.