8.3 Shippers shall cause the Operator of each Point of Receipt and
each Point of Delivery designated in any nomination pursuant to
the NAESB standards as referenced on Tariff Sheet Nos. 190 and 191
to confirm all such nominations or changes to nominations to KPC
in writing, by facsimile transmission or via the IEC as provided
for in this Section 8, prior to implementation by KPC.
8.4 (a) KPC will accept one pre-determined allocation (PDA)
methodology per allocation period. The upstream or
downstream party providing the point confirmation will
submit the PDA to the allocating party after or during the
confirmation and before the start of the gas day. The types
of Allocation Methodologies is a list from which two (2)
parties may agree. If the two (2) parties cannot agree upon
an allocation methodology, pro rata based upon confirmed
nominations should be used as the default method. The party
responsible for custody transfer (the party performing the
measurement function) should provide the allocation.
(b) Changes to the daily allocation methodology may be made
during the Month. Such changes must be submitted one Day in
advance of the effective date and shall be effective
prospectively. No retroactive reallocations of any
transactions shall be permitted.
(c) At a location which is not covered by an OBA, KPC will
allocate Shippers at the Shippers' contract level or higher.
KPC is not required to allocate to a lower level or accept
accounting allocation instructions from the Shipper (i.e.,
neither Pre-determined Allocations (PDAs) nor Shipper ranks
supplied in the nominations.)
(d) At a location which is not covered by an OBA, a Confirming
Party should submit a Pre-determined Allocation (PDA) to the
allocating party at a level that is based on the allocating
party's business practice, but in no event, will such PDA be
at a lower level (more detailed) than that level of
information exchanged between such parties during their
confirmation process.
(e) A pre-determined Allocation (PDA) may not be used to
allocate gas to a nominatable transaction that was not
identified in the nomination or confirmation process, as
applicable, absent prior mutual agreement among the
Confirming Parties and the party being allocated to in such
transaction. In the event of a conflict between this
standard and KPC' existing Tariff or general terms and