greater than 2 MMcf per Day. The SREI shall be determined by
tests at the orifice taps and shall be performed on the full
operating range of the compressor.
4.6 When the information necessary for billing purposes is in the
control of the operator of the measuring facility and not KPC's
control, then the operator of that measuring facility shall
furnish to KPC daily operational volumes of the previous twenty-
four hours within a twenty-four hour period upon completion of the
gas Day. In addition, the operator of the measuring facility
shall furnish actual volume information to KPC on or before the
fifth Day following each Month. The cutoff for the closing of
measurement is five (5) business days after the business month.
If volumes are not available, an estimate shall be provided by the
operator of the measuring facility to KPC by no later than 3:00
p.m. Central time on the fifth Day of each Month. If an estimate
is not made by the operator of the measuring facility, then KPC
shall estimate a Quantity of Gas based on the best information
available.
For treatment of measurement prior period adjustments, treat the
adjustment by taking it back to the production month. A meter
adjustment becomes a prior period adjustment after the fifth (5th)
business day following the business month. Reporting measurement
prior period adjustments will be reflected by restating the line
item with the new total quantity for the day and month.
5. RESPONSIBILITY DURING TRANSPORTATION
As between KPC and Shipper, KPC shall be deemed to be in control and
possession of the Gas transported hereunder only after the Gas is received at
the Point of Receipt, and before it is delivered to or for the account of
Shipper at the Point of Delivery. Shipper shall be deemed to be in control and
possession at all other times. Whichever of KPC or Shipper is deemed to be in
control and possession of the Gas shall be responsible for and shall indemnify
the other party with respect to any losses, injuries, claims, liabilities or
damages caused thereby and occurring while the Gas is in its possession.
6. PROCEDURES FOR REQUESTING SERVICE RIGHTS
6.1 Persons desiring Transportation or Sales service must deliver a
valid executed request for service rights through the IEC System