Quest Pipelines (Kpc)
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/2010, Docket: RP10-394-000, Status: Effective
First Revised Sheet No. 81 First Revised Sheet No. 81
Superseding: Original Sheet No. 81
RATE SCHEDULE SCT (Continued)
SMALL CUSTOMER TRANSPORTATION SERVICE
(c) Overrun Charge for Takes During Operational Flow Orders and
Extreme Conditions
When Gas throughput approaches capacity on any portion of
KPC's system, KPC may issue an OFO or an extreme condition
situation as to that portion of the system by notifying
Shippers through the EBB System and telephone or facsimile
communication. Once these situations are in effect, they
shall continue until KPC notifies Shippers to the contrary.
During an OFO or extreme conditions situation the applicable
charge per Dt. for overrun quantities in excess of the MDCQ
shall be those as defined in Section 12.13 of this General
Terms and Conditions.
3.4 Range of Rates
Any rate applicable to a Shipper for service hereunder, by
reference to the effective FERC Tariff Sheet Nos. 49 and 50 shall
be the applicable Maximum Rate(s) set forth thereon. If an amount
less than the applicable Maximum Rate(s) and not less than the
applicable Minimum Rate(s) is agreed upon, such amount shall be
applicable prospectively.
3.5 Fuel Reimbursement
Shipper shall reimburse KPC in kind for fuel usage and lost or
unaccounted for Gas pursuant to the terms and conditions of the
Service Agreement and as stated on the effective FERC Tariff Sheet
No. 57 for service hereunder.
3.6 Balancing Charges
If balancing charges are incurred in accordance with Section 12 of
the General Terms and Conditions, then such balancing charges
shall also be applicable.