Quest Pipelines (Kpc)
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/01/2008, Docket: RP08-174-000, Status: Effective
Original Sheet No. 75 Original Sheet No. 75 : Effective
RATE SCHEDULE FT (Continued)
FIRM TRANSPORTATION SERVICE
be as set forth on the effective Tariff Sheet Nos. 21 and 22
for service within the same Zone only; if the Point(s) of
Receipt and the Point(s) of Delivery are located in
different zones, the applicable rates shall be derived by
adding the effective rates for service in the multiple
Zones.
3.2 ACA and Other Charges
Shipper shall pay all ACA and other charges specified in the
General Terms and Conditions or which otherwise may be applicable
to service under these Rate Schedules from time to time.
3.3 Overrun Charges
(a) Overrun Charge for Takes in Excess of MDCQ
If during one or more Days in the billing Month Shipper
takes Quantities of Gas in excess of the applicable Maximum
Daily Contract Quantity as stated in the Service Agreement
(hereinafter called overrun quantities) for firm service
hereunder, Shipper shall be subject to an overrun charge in
addition to the applicable reservation charge and any
balancing charges that may be applicable pursuant to Section
12 of the General Terms and Conditions. Subject to the
provisions of Section 3.3(b) of this Rate Schedule, the
applicable charge per Dt. for such overrun quantities shall
be as set forth on the effective Tariff Sheet Nos. 21 and
22.
(b) Takes In Excess of Permissible Hourly Deliveries
If, pursuant to Section 5 hereof, Shipper has been notified
that it must limit hourly takes of the Quantities nominated
for delivery at the Point(s) of Delivery, Shipper must use
its best efforts to limit its takes of the Quantities
nominated for delivery at the Point(s) of Delivery as soon
as possible, but in no event later than two hours following