Kinder Morgan Interstate Gas Transmission LLC

Second Revised Volume No. 1-C

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 12/28/1999, Docket: GT00- 19-000, Status: Effective

Original Sheet No. 9 Original Sheet No. 9 : Superseded

 

 

 

RATE SCHEDULE FT-BW - continued

 

3.5 NOMINATIONS AT PRIMARY OR SECONDARY RECEIPT POINT(S). Shippers

served under this FT-BW Rate Schedule may nominate at either

primary or secondary receipt points. Nominations at secondary

points will interrupt IT-BW service if necessary in order to

secure sufficient capacity to meet the firm service requirements.

However, interruption shall not occur until Transporter has given

affected IT-BW service customers 24-hour notice, unless

interruption is due to an Intra-day nomination in which Section 6

of this Rate Schedule will apply.

 

3.6 MAXIMUM DAILY RECEIPT QUANTITY (At Individual Receipt Point). The

Maximum Daily Receipt Quantity (MDRQ) shall mean the maximum

quantity of natural gas which Transporter agrees to receive on any

day at an indicated Primary Receipt Point as specified in the

executed Service Agreement; provided however, that the sum of the

Maximum Daily Receipt Quantities (MDRQs) at all Primary Receipt

Points, less any Fuel Reimbursement Quantity and other deductions,

shall not be in excess of the Maximum Daily Transportation

Quantity (MDTQ) specified in the executed Service Agreement.

 

3.7 PRIMARY DELIVERY POINT(S). Primary Delivery Point(s) are those

delivery points to which the Shipper desires firm service and

which are set forth in the Service Agreement. The volume

specified for a Primary Delivery Point shall not exceed the

available firm capacity at that point.

 

3.8 SECONDARY DELIVERY POINT(S). A Shipper holding FT-BW service may

nominate any number of Secondary Delivery Points. The sum of the

nominated quantities at all Primary and Secondary Delivery Points,

less any Fuel Reimbursement Quantity and other deductions, shall

not exceed the MDTQ of the Service Agreement on any given day.

 

3.9 NOMINATIONS AT PRIMARY OR SECONDARY DELIVERY POINT(S). Shippers

served under this FT-BW Rate Schedule may nominate at either

primary or secondary delivery points. Nominations at secondary

points will interrupt affected IT-BW service if necessary in order

to secure sufficient capacity to meet the firm service

requirements. However, interruption shall not occur until

Transporter has given IT-BW service customers 24-hour notice,

Unless interruption is due to an Intra-day nomination in which

Section 6 of this Rate Schedule will apply.