Kinder Morgan Interstate Gas Transmission LLC

Second Revised Volume No. 1-D

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 03/27/2000, Docket: RP00-316-001, Status: Effective

First Revised Sheet No. 41 First Revised Sheet No. 41 : Effective

Superseding: Original Sheet No. 41

 

GENERAL TERMS AND CONDITIONS FOR SERVICES - continued

 

subsequent deadlines set forth in this Section 23, but Transporter

shall make a reasonable attempt to adhere to such deadlines.

Transporter shall publish standards relating to such computer

diskettes, but it is the responsibility of the Releasing Shipper to

develop and provide the working computer diskette. The Releasing

Shipper shall warrant that the computer diskette conforms to the bid

evaluation procedure in the Capacity Release Request.

 

(b) The term of any release of capacity sought under

this Section 23 shall be at least one full day and shall not exceed

the remaining term of the Eligible Firm Transportation Agreement.

 

(c) The quantity sought to be released under a Capacity

Release Request shall not be less than one hundred (100) Dth per Day.

 

(d) (1) No capacity release under this Section 23 shall

result in an increase in the total capacity set forth in the Eligible

Firm Transportation Agreement with the Original Shipper for any

segment of a path covered by such Eligible Firm Transportation

Agreement. In the event a path is segmented by a capacity release

under this Section 23, the upstream path segment shall receive all

secondary points upstream of the break point and the downstream path

segment shall receive all secondary points downstream of the break

point. The direction of "forward" flow for path segments must be the

same direction of "forward" flow for the original path. The

Replacement Shipper may nominate service at Receipt and Delivery

Points for the path segment that result in a reverse flow from the

original path; however, such service will be treated as being outside

of the path as provided in Section 3 of Rate Schedule FTS in

Volume 1-C.

 

(2) The commodity and reservation charges

applicable to deliveries to and from newly created path endpoints as

a result of a path release shall be determined in accordance with

Section 3 of Rate Schedule FTS in Volume 1-C; provided, however, that

the bid may exceed the maximum reservation charge through September

30, 2002, to the extent the rate ceilings have been waived for

released capacity contracts of less than one (1) year pursuant to 18