GENERAL TERMS AND CONDITIONS FOR SERVICE - continued
22.9 Term Coordination
In some circumstances, Shipper may desire to extend and
coordinate the term of its service agreement with Transporter
("Transporter Service Agreement") with the term of Shipper's
service agreement ("Other Pipeline Service Agreement") on a
planned, but not yet constructed, natural gas pipeline project
("Project") which will interconnect with Transporter and where
the in-service date of the Project cannot be definitively
ascertained. In such circumstance, Transporter shall agree, on a
non-discriminatory basis, as part of the term provision of the
Transporter Service Agreement that similarly situated Shippers
may elect to extend the contract term of the Transporter Service
Agreement, and any associated rate agreement, to match the term
of the Other Pipeline Service Agreement, subject to the following
conditions:
a. the Project is placed in service and Shipper is a shipper
thereon; and
b. Transporter has available capacity which has been posted and
Shipper obtains such capacity on Transporter for the
extension period of the Transporter Service Agreement
through an Open Season or under otherwise applicable
procedures.