Kinder Morgan Interstate Gas Transmission LLC
Fourth Revised Volume No. 1-B
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/03/2007, Docket: RP07-441-001, Status: Effective
Substitute Original Sheet No. 37B Substitute Original Sheet No. 37B : Effective
GENERAL TERMS AND CONDITIONS, continued
C. If Shipper and Transporter agree to rollover a Service
Agreement pursuant to Section 18.7A or B, the Right of First
Refusal procedure under this Section 18 shall not be
necessary. Should Shipper secure the Right of First Refusal
under an amended Service Agreement that resulted from a
rollover, Shipper shall retain full rights to utilize such
Right of First Refusal as it may apply during the term of
the amended Service Agreement.
19. DULY CONSTITUTED AUTHORITIES
This FERC Gas Tariff, including these General Terms and Conditions and
the respective obligations of the parties under the Service Agreement,
is subject to valid current and future laws, orders, rules and
regulations of duly constituted authorities having jurisdiction. Each
Party's obligations under a Service Agreement is conditioned upon
obtaining authorization from the appropriate governmental authorities.