Kinder Morgan Interstate Gas Transmission LLC
Fourth Revised Volume No. 1-B
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2002, Docket: RP02-419-000, Status: Effective
Third Revised Sheet No. 9A Third Revised Sheet No. 9A : Effective
Superseding: Second Revised Sheet No. 9A
GENERAL TERMS AND CONDITIONS FOR SERVICES - continued
c. The Intra-Day 1 Nomination Cycle: 10:00 a.m. for nominations
leaving control of the nominating party; 10:15 a.m. for receipt of
nominations by Transporter; 10:30 a.m. to send Quick response;
1:00 p.m. for receipt of completed confirmations by Transporter
from upstream and downstream connected parties; 2:00 p.m. for
transporter to provide scheduled quantities to affected shippers
and point operators, and to provide scheduled quantities to bumped
parties (notice to bumped parties), (CT on the gas Day).
Scheduled quantities resulting from Intra-Day 1 Nominations should
be effective at 5:00 p.m. gas Day.
d. The Intra-Day 2 Nomination Cycle: 5:00 p.m. for nominations
leaving control of the nominating party; 5:15 p.m. for receipt of
nominations by Transporter; 5:30 p.m. to send Quick Response; 8:00
p.m. for receipt of completed confirmations by Transporter from
upstream and downstream connected parties; 9:00 p.m. for
Transporter to provide scheduled quantities to affected shippers
and point operators (CT on the gas Day). Scheduled quantities
resulting from Intra-Day 2 Nominations should be effective at 9:00
p.m. on gas Day. Bumping is not allowed during the Intra-Day 2
Nomination Cycle.
e. For purposes of Section 3.2 (b)(c) and (d), "provide" shall
mean, for transmittals pursuant to standards 1.4.x, receipt at the
designated site, and for purposes of other forms of transmittal,
it shall mean send or post.
f. The rights of a Releasing shipper to recall capacity within
any nomination cycle shall be governed by Section 23.14 of these
General Terms and Conditions.
g. A Shipper which has been awarded firm capacity in a capacity
release may submit a nomination using such capacity at the next
available opportunity for nominations under this Section 3.2 which
occurs on or after the time capacity is awarded, including an
intraday nomination in either the Intra-day 1 or the Intra-day 2
Nomination Cycle, and which is consistent with Section 23.9(d) of
these General Terms and Conditions.