Kinder Morgan Interstate Gas Transmission LLC

Fourth Revised Volume No. 1-A

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 06/01/2004, Docket: CP03- 39-001, Status: Effective

Original Sheet No. 183 Original Sheet No. 183 : Effective

 

RATE SCHEDULE CMC-2 (Continued)

 

C. Upon expiration of the CMC-2 Agreement, any gas remaining in

storage will be treated and billed as if it were a PALS

Agreement. Any gas remaining in inventory sixty (60) days

after expiration of the CMC-2 Agreement will be confiscated

by Transporter.

 

6.3 Intra-day Nominations

 

In addition to the intra-day nominations under Section 3 of the

General Terms and Conditions of this Tariff, Shipper may make two

out-of-cycle (OOC) intra-day nominations per day to be effective

on a prospective basis on any hour of the Gas Day if such intra-

day nomination is submitted at least 2 hours prior to the time

the OOC intra-day nomination is to become effective. Shipper

must confirm service availability with Transporter's Gas Control

prior to submitting the OOC nomination by both telephone and

email. The total nominations for any hour of the Gas Day shall

not exceed 1/24 of Shipper's MDRQ or MDDQ, unless otherwise

authorized by Transporter. Shipper's OOC intra-day nomination

shall be implemented upon confirmation by the operators of the

Points of Receipt and Delivery and if Transporter's system

operating conditions will allow such OOC intra-day nomination,

except that such an OOC intra-day nomination will not be

implemented to the extent it would result in a change to any

other Shipper's scheduled and flowing quantities for that Gas

Day. Quantities shall be deemed to be flowing if the operator at

the Point of Receipt and Point of Delivery has confirmed

Shipper's nomination.

 

Shipper must nominate separately any injection or withdrawal

intra-day nominations for both OOC and NAESB cycle intra-day

nominations.

 

6.4 Shipper may not effectuate transfers to or from volumes stored

under this Rate Schedule CMC-2 that resolve transportation

imbalances existing under FT, IT or NNS (including SCS rate

convention customers) Agreements.

 

6.5 In the event of Capacity Release under this CMC-2 Rate Schedule,

in the aggregate or which results in separate storage and

transportation components, the releasing Shipper's WQ and IQ shall

be reduced by the corresponding amount of MDRQ and MDDQ released,

pursuant to Section 3 of this CMC-1 Rate Schedule.