Kinder Morgan Interstate Gas Transmission LLC
Fourth Revised Volume No. 1-A
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/2004, Docket: CP03- 39-001, Status: Effective
First Revised Sheet No. 157 First Revised Sheet No. 157 : Effective
Superseding: Original Sheet No. 157
RATE SCHEDULE CMC-1 (continued)
4.3 The information required for a valid request shall be as follows:
A. GAS QUANTITIES
The request shall specify in Dth the Maximum Storage
Contract Volume ("MSV"), the MDRQ for each primary point,
which in aggregate shall equal the product of 0.0064 and
the MSV, and MDDQ for each primary point, which in
aggregate shall equal the product of 0.0104 and the MSV,
with the MDRQ and MDDQ stated exclusive of the applicable
Fuel, Loss and Unaccounted For Reimbursement Quantity. The
availability of the MSV, MDRQ and MDDQ on any day are
subject to the provisions of this Rate Schedule CMC-1 and
the General Term and Conditions of Transporter's FERC Gas
Tariff.
B. RECEIPT POINT(S)
The request shall specify the primary point(s) at which
Shipper desires Transporter to receive gas and including
the associated MDRQ.
C. DELIVERY POINT(S)
The request shall specify the primary point(s) at which
Shipper desires Transporter to deliver gas and including
the associated MDDQ.
D. LIMITATION OF POINTS
A Shipper may request only those points listed on the MPL as
designated CMC-1 Receipt and Delivery Points.
E. TERM OF SERVICE
The request shall specify the date service is requested to
commence, and the date service is requested to terminate.
However, the term of service hereunder shall be no less than
one (1) year, unless otherwise agreed to in writing by
Transporter, and shall be set forth in the CMC-1 Service
Agreement between Shipper and Transporter.
F. CREDIT
Acceptance of a request is contingent upon a satisfactory
credit appraisal by Transporter in accordance with the
General Terms and Conditions of this Tariff.