Kinder Morgan Interstate Gas Transmission LLC

Fourth Revised Volume No. 1-A

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 03/01/2003, Docket: RP03-245-000, Status: Effective

Original Sheet No. 148U.12 Original Sheet No. 148U.12 : Effective

 

RATE SCHEDULE S-PALS

 

6.3 (a) Shipper shall reimburse Transporter within five (5) days

after costs have been incurred by Transporter for all fees

required by the FERC or any regulatory body including, but

not limited to, filing, reporting, and application fees to

the extent such fees are specifically related to service

for that Shipper hereunder and are not generally applicable

fees (such as general rate case filing fees).

 

(b) If Transporter constructs, acquires or modifies any

facilities to perform service hereunder, then, as specified

in an agreement related thereto between the parties,

either:

 

(1) Shipper shall reimburse Transporter for the cost of

such facilities or facility modifications as described

in Section 5.3(a) of the Interruptible Transportation

service Rate Schedule of this Tariff; or

 

(2) Transporter shall assess a monthly charge reflecting

such facility costs.

 

6.4 (a) Transporter shall have the unilateral right to file with

any appropriate regulatory authority and make changes

effective in: (1) the rates and charges applicable under

this Rate Schedule S-PALS, including both the level and

design of such rates and charges; and/or (2) the terms and

conditions of this Rate Schedule S-PALS. Transporter

agrees that Shipper may protest or contest the

aforementioned filings, or may seek authorization from duly

constituted regulatory authorities for such adjustment of

Transporter's existing FERC Gas Tariff as may be found

necessary to assure that its provisions are just and

reasonable.