RATE SCHEDULE FTS
-----------------
7. RECEIPT AND DELIVERY POINTS AND UPSTREAM AND DOWNSTREAM ARRANGEMENTS
(a) The primary Receipt Points for gas tendered to
Trailblazer for transportation hereunder and the primary Delivery
Points for gas delivered by Trailblazer to Shipper (or to a third
party on behalf of Shipper) hereunder shall be specified in the FTS
Agreement. For each individual primary Receipt and Delivery Point,
and for the aggregate of all such points, Trailblazer's maximum
obligation to accept and deliver gas on a firm basis shall be
specified in MMBtus in the FTS Agreement. The sum of the MDQs for
primary Receipt Points and the sum of the MDQs for primary Delivery
Points shall not exceed the aggregate MDQ. Shipper may utilize any
and all points as secondary Receipt or Delivery Points as specified
in the General Terms and Conditions of this Tariff.
(b) Conditions of delivery at Receipt and Delivery Points
are set out in the General Terms and Conditions of this Tariff.
(c) Shipper shall make all necessary arrangements with other
parties: (1) at or upstream of the Receipt Point(s) where gas is
tendered to Trailblazer hereunder; and (2) at or downstream of the
Delivery Point(s) where Trailblazer delivers gas hereunder to or for
the account of Shipper. Such arrangements must be consistent with
this Rate Schedule FTS and must be coordinated with Trailblazer.
8. OVERRUN SERVICE
Upon request of Shipper, Trailblazer may (but is not
obligated to) receive, transport, and deliver on any day quantities
of natural gas in excess of Shipper's MDQ under the FTS Agreement
when, in Trailblazer's reasonable judgment, the capacity and
operating capability of its System will permit such receipt,
transportation and delivery without impairing the ability of
Trailblazer to meet its other obligations. In granting requests for
overrun service, Trailblazer shall act in a manner consistent with
the overrun service priorities set out in the General Terms and
Conditions of this Tariff. Shipper shall pay Trailblazer the
applicable rate for Authorized Overrun Service set forth in this
Tariff. Except for Authorized Overrun Service hereunder, Shipper
shall pay Trailblazer an Unauthorized Overrun Charge of $10 per
MMBtu if gas tendered to Trailblazer or deliveries to Shipper under
an FTS Agreement exceed the MDQ under such FTS Agreement.