Trailblazer Pipeline Company
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 01/01/1998, Docket: RP97-408-000, Status: Effective
Fourth Revised Sheet No. 11 Fourth Revised Sheet No. 11 : Superseded
Superseding: Third Revised Sheet No. 11
RATE SCHEDULE T
---------------
operational date of a System expansion occurs on any day other than
the first day of a month, then the Demand Charges for such month
relating to the increase in capacity resulting from the System
expansion shall be reduced proportionately based on the ratio of the
number of days that expanded transportation service was not in
effect to the total number of days in such month.
4.3 COMMODITY RATE
In addition to the monthly Demand Charge, Shipper shall
each month pay Trailblazer a Commodity Charge in an amount equal to
the product of: (a) volumes (in Dth) received by Trailblazer from
Shipper at the points of receipt in Appendix A to the service
agreement during such month; and (b) Trailblazer's currently
effective commodity rate as set forth in the Currently Effective
Rates section of this Tariff.
4.4 TARIFF CHANGES
Trailblazer may apply to the FERC for changes in this
Rate Schedule, from time to time, without prejudice to the rights of
any Shipper to contest such changes.
5. FLEXIBLE POINTS
Shippers under this Rate Schedule T shall be accorded
the same flexibility with regard to primary, secondary and pooling
points as are provided to firm Shippers under Rate Schedule FTS.
6. MINIMUM BILL
After a Shipper's Contract Demand becomes effective,
such Shipper shall be obligated to pay monthly, at least a minimum
bill in the amount of the Shipper's Demand Charge computed pursuant
to Section 4.1 under all circumstances for the remaining term of the
service agreement between Trailblazer and such Shipper. Shipper's
obligation to pay the minimum bill shall not terminate nor be
reduced by any circumstances including, but not limited to, events
of Force Majeure, non-delivery of gas, suspension or termination of
operation or abandonment of the System, or any other circumstances
or events within or without the control or responsibility of the
Trailblazer.