GENERAL TERMS AND CONDITIONS
----------------------------
26. POSSESSION OF GAS, TITLE AND RESPONSIBILITY
Shipper warrants that it will at the time of delivery to
Trailblazer have good title to all gas so delivered free and clear
of all liens, encumbrances and claims whatsoever. As between
Shipper and Trailblazer, Shipper shall be deemed to be in control
and possession of the gas and responsible for and hold Trailblazer
harmless of and from any damage or injury caused thereby until it
shall have been delivered to Trailblazer at the Receipt Point(s),
after which Trailblazer shall be deemed to be in control and
possession of such gas until its delivery to Shipper, or for
Shipper's account at the Delivery Point(s) and while in such
possession Trailblazer shall be responsible therefor and hold
Shipper harmless of and from any damage or injury caused thereby.
Trailblazer shall have no responsibility with respect to any gas
on account of anything which may be done, happen or arise with
respect to said gas until it is received by Trailblazer. Shipper
shall have no responsibility with respect to said gas after its
receipt by Trailblazer or on/account of anything which may be
done, happen or arise with respect to said gas after such receipt
until its delivery to Shipper, or for Shipper's account, at the
Delivery Point(s). The point of the division of responsibility
shall be the point of interconnection between the facilities of
Trailblazer and Shipper, or their respective agents, at the
Receipt or Delivery Point(s), as applicable. The foregoing
provisions of this Section shall not relieve either party from
responsibility for acts of gross negligence or willful misconduct
of such party, its agents or employees.