Questar Southern Trails Pipeline Company

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 10/14/2008, Docket: CP99-163-004, Status: Effective

Second Revised Sheet No. 66 Second Revised Sheet No. 66

Superseding: First Revised Sheet No. 66

 

GENERAL TERMS AND CONDITIONS

 

8.2 Posting. Southern Trails shall post on Questline the terms and

conditions of the available capacity under the expiring contract as follows:

 

(a) RDC stated in Dth/day.

 

(b) Receipt and delivery points at which capacity is available

and the firm quantities at such points.

 

(c) Effective date.

 

(d) Term.

 

(e) Applicable rates for the service.

 

(f) That capacity is subject to right of first refusal.

 

8.3 Bidding. Capacity will be made available on a nondiscriminatory

basis and may be acquired through the bidding process described in § 6 of

these General Terms and Conditions.

 

(a) A Shipper desiring to acquire the available capacity shall

place a bid with Southern Trails, via Questline, during the bid period. The

bid shall be binding once received by Southern Trails and may not be withdrawn

by the bidding Shipper.

 

(b) A Shipper's bid must include all information included in §

6 of these General Terms and Conditions.

 

8.4 Terms and Acceptance.

 

(a) Southern Trails shall not be obligated to accept any bid for

the capacity at less than the maximum applicable tariff rate or for a term

greater than the term posted in the notice of available unsubscribed capacity.

Upon acceptance of a bid, Southern Trails shall inform the existing Shipper of

the terms of the bid to permit Shipper to exercise its right of first refusal.

A Shipper exercising its right of first refusal must match the highest bid.

The existing Shipper shall have five days to inform Southern Trails that it

agrees to match the bid.

 

(b) If the existing Shipper notifies Southern Trails that it

elects to match the terms of price and duration