Questar Pipeline Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/25/2005, Docket: RP05-401-000, Status: Effective
Seventh Revised Sheet No. 116 Seventh Revised Sheet No. 116 : Effective
Superseding: Sixth Revised Sheet No. 116
PART 2
GENERAL TERMS AND CONDITIONS
(Continued)
WITHDRAWAL ALLOCATION = (X/Y)*Z
X = Shipper's estimated recoverable working gas remaining in storage
at a particular reservoir
Y = Sum of the estimated recoverable working gas remaining of all PKS
shippers at that reservoir
Z = Available withdrawal capacity on any day at that reservoir
* = Multiplication operator
If any Rate Schedule PKS shipper elects, on any day, not to utilize all
or any portion of its withdrawal allocation at a particular reservoir, the
amount not used shall be allocated to all remaining Rate Schedule PKS shippers
that desire additional withdrawal allocation, at that reservoir, by using the
above formula as modified to exclude the data related to those shippers who
have received all of the withdrawal capacity that was requested by them.
If any firm withdrawal capacity remains unclaimed after completion of
the above allocation procedure, it shall be available to provide parking and
loaning service under Rate Schedule PAL2 with the highest rate paid being
given the highest priority. When two or more shippers are paying the same
rate, available capacity will be allocated pro rata up to the level requested,
to those PAL2 shippers that are paying the same rate. This procedure will
continue until (1) all the requests are filled or (2) all available withdrawal
capacity is utilized.
9.3 Commencement of Service. Starting no later than 9:00 a.m. on the
day immediately following the calendar day nominations are received, Questar
will commence injecting or withdrawing quantities of gas less any appropriate
reduction for fuel reimbursement according to § 14 of this Part 2.