Questar Pipeline Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/25/2005, Docket: RP05-401-000, Status: Effective
Second Revised Sheet No. 88C Second Revised Sheet No. 88C : Effective
Superseding: First Revised Sheet No. 88C
PART 1
GENERAL TERMS AND CONDITIONS
(Continued)
(b) By using the registration of any check meter or meters, if
installed and accurately registering, or, in the absence of (a) and (b);
(c) By estimating the quantity of gas received or delivered based
on receipts or deliveries during preceding periods under similar conditions
when the measurement equipment was registering accurately.
14.14 Preservation of Records. Questar will retain data as may be
required by appropriate authority.
14.15 Measurement Data Corrections. Measurement data corrections will
be processed within six months of the production month with a three-month
rebuttal period. This standard will not apply in the case of deliberate
omission or misrepresentation or mutual mistake of fact. Parties' other
statutory or contractual rights shall not otherwise be diminished by this
standard (NAESB 2.3.14).
14.16 Cutoff. The cutoff for the closing of measurement is five
business days after the business month.
15. FACILITIES
Questar is not required to construct or acquire any additional
facilities to provide requested transportation service. If Questar installs
facilities at the request of a shipper, that shipper shall make full payment
to Questar for