PART 1
GENERAL TERMS AND CONDITIONS
(Continued)
(a) With respect to the timely nomination/
confirmation process at a receipt or delivery point, in the
absence of agreement to the contrary, the lesser of the
confirmation quantities should be the confirmed quantity.
If there is no response to a Request For Confirmation or an
unsolicited Confirmation Response, the lesser of the
confirmation quantity or the previously scheduled quantity
should be the new confirmed quantity.
(b) With respect to the processing of requests for
increases during the intra-day nomination/confirmation
process, in the absence of agreement to the contrary, the
lesser of the confirmation quantities should be the new
confirmed quantity. If there is no response to a Request
For Confirmation or an unsolicited Confirmation Response,
the previously scheduled quantity should be the new
confirmed quantity.
(c) With respect to the processing of requests for
decreases during the intra-day nomination/confirmation
process, in the absence of agreement to the contrary, the
lesser of the confirmation quantities should be the new
confirmed quantity, but in any event no less than the
elapsed-prorated-scheduled quantity. If there is no
response to a Request For Confirmation or an unsolicited
Confirmation Response, the greater of the confirmation
quantity or the elapsed-prorated-scheduled quantity should
be the new confirmed quantity.
(d) With respect to 11.3 (a)-(c) above, if there
is no response to a Request For Confirmation or an
unsolicited Confirmation Response, Questar shall provide the
shipper with the following information to explain why the
nomination failed, as applicable:
(1) Questar did not conduct the confirmation;
(2) Shipper is told by Questar that the upstream
confirming party did not conduct the confirmation;
(3) Shipper is told by Questar that the upstream
shipper did not have the gas or submit the nomination;
(4) Shipper is told by Questar that the downstream
confirming party did not conduct the confirmation;