Questar Pipeline Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/21/2005, Docket: RP05-349-000, Status: Effective
First Revised Sheet No. 36 First Revised Sheet No. 36 : Effective
Superseding: Sub. Original Sheet No. 36
RATE SCHEDULE PAL2
PARKING AND LOANING SERVICE
rate in equal amounts up to the level requested. This procedure will continue
until (1) all the requests are filled or (2) all available capacity is
utilized.
(e) (i) If needed to protect the operational integrity of
Questar's system, shipper may be required, within 72 hours (three nomination
days) of notice by Questar, to nominate delivery of all, or any portion of,
quantities of gas parked on Questar's system or to nominate receipt of all, or
any portion of, loaned gas quantities at any non-constrained delivery or
receipt point, respectively. This § 3(e)(i) may be enforced to the extent it
impairs Questar's ability to provide service to another customer or threatens
or impairs Questar's system integrity.
(ii) Any parked gas quantity not scheduled to be removed
within three nomination days of Questar's notice shall be retained by Questar
and cashed out at the Tier 2 index gas price as provided in § 12.6 of the
General Terms and Conditions of Part 1 of this tariff.
(iii) Shipper shall reimburse Questar at the Tier 2 index
gas price as provided in § 12.6 of the General Terms and Conditions of Part 1
of this tariff for any loaned gas quantities not scheduled to be returned
within the three-day nomination period.
(iv) Questar will refund any excess revenues pursuant to §
12.7 of the General Terms and Conditions of Part 1 of this tariff.
(f) (i) Shipper may be required, upon notification from Questar
for reasons other than operational (see (iii) below), to cease or reduce
deliveries to or receipts from its parking account within the gas day, as
rapidly as is consistent with Questar's operating capabilities. If delivery
capacity is available on Questar's system and shipper fails to arrange to take
deliveries of parked gas quantities as required by Questar within 30 days of
Questar's notice, that portion of shipper's parking account, of which shipper
did not take delivery shall be retained by Questar and cashed out at the Tier
1 index gas price set forth in § 12.6 of the General Terms and Conditions of
Part 1 of this tariff.
(ii) Shipper may be required, upon notification from
Questar for reasons other than operational