Canyon Creek Compression Company
First Revised Volume No. 1A
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/14/1991, Docket: MT90- 5-002, Status: Effective
First Revised Sheet No. 39 First Revised Sheet No. 39 : Superseded
Superseding: Original Sheet No. 39
RATE SCHEDULE ICS
-----------------
(d) The state(s) of the ultimate end user of the gas;
(e) The appropriate area code(s) for the producing area
where the field or well producing the gas to be transported is
located pursuant to the codes provided in DOE EIA-0370; Oil and Gas
Field Code Master List;
(f) The identity of the Customer requesting service,
including designating whether the Customer is a local distribution
company, an interstate pipeline, an intrastate pipeline, an end
user, a producer, or a marketer; and
(g) Whether and by how much the cost of the gas to the
affiliated marketer exceeds the price received for the sale of the
gas by the affiliated marketer, after deducting associated costs,
including those incurred for transportation.
6. TERM
6.1 The term for interruptible service under this Rate
Schedule ICS shall be as set forth in the ICS Agreement between
Customer and Canyon. Canyon may terminate the ICS Agreement if
Customer fails to deliver gas during any two (2) consecutive months
when capacity is available, unless Customer's failure to deliver gas
was attributable to circumstances of Force Majeure.
6.2 Should at any time during the term of an executed ICS
Agreement, Canyon and Customer agree to extend the term of such
Agreement provided that the MDQ in the rollover agreement does not
exceed the MDQ in the prior Agreement and no other provisions are
changed other than possibly the rate the Customer pays, Customer's
initial contract date shall be retained for purposes of establishing
priority under Section 3 hereof. The addition of new point(s) of
receipt or delivery shall be considered a new request for service
for purposes of setting priorities in Section 3 hereof.
7. RATE
7.1 Customer shall pay Canyon each month under this Rate
Schedule ICS a one-part Commodity Charge for each unit of gas
received for transportation and compression together with such other
charges as are identified in Sections 9, 10, 11 and 14 of this Rate
Schedule ICS. The maximum monthly Commodity Charge shall be the
applicable maximum unit rate set out in this Tariff multiplied by
the quantity of gas received by Canyon for Customer during the
billing month.