Canyon Creek Compression Company

Third Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 10/01/2002, Docket: RP02-418-000, Status: Effective

Third Revised Sheet No. 121B Third Revised Sheet No. 121B : Effective

Superseding: Second Revised Sheet No. 121B

GENERAL TERMS AND CONDITIONS

----------------------------

 

(c) The Intra-day 1 Nomination Cycle: 10:00 a.m. for

nominations leaving control of the nominating party; 10:15 a.m. for

receipt of nominations by Canyon; 10:30 a.m. to send Quick Response;

1:00 p.m. for receipt of completed confirmations by Canyon from upstream

and downstream connected parties; 2:00 p.m. for Canyon to provide

scheduled quantities to affected shippers and point operators, and to

provide scheduled quantities to bumped parties (notice to bumped

parties), (central clock time on the gas Day). Scheduled quantities

resulting from Intra-day 1 Nominations should be effective at 5:00 p.m.

on the gas Day.

 

(d) The Intra-day 2 Nomination Cycle: 5:00 p.m. for

nominations leaving control of the nominating party; 5:15 p.m. for

receipt of nominations by Canyon; 5:30 p.m. to send Quick Response;

8:00 p.m. for receipt of completed confirmations by Canyon from upstream

and downstream connected parties; 9:00 p.m. for Canyon to provide

scheduled quantities to affected shippers and point operators (central

clock time on the gas Day). Scheduled quantities resulting from Intra-

day 2 Nominations should be effective at 9:00 p.m. on the gas Day.

Bumping is not allowed during the Intra-day 2 Nomination Cycle.

 

(e) For purposes of Section 6.2 (b), (c), and (d),

"provide" shall mean, for transmittals pursuant to standards 1.4.x,

receipt at the designated site, and for purposes of other forms of

transmittal, it shall mean send or post.

 

(f) The rights of a Releasing Shipper to recall capacity

within any nomination cycle shall be governed by Section 16.14 of these

General Terms and Conditions.

 

(g) A Shipper which has been awarded firm capacity in a

capacity release may submit a nomination using such capacity at the next

available opportunity for nominations under this Section 9.2 which

occurs on or after the time capacity is awarded, including an intraday

nomination in either the Intra-day 1 or the Intra-day 2 Nomination

Cycle, and which is consistent with Section 16.9(d) of these General

Terms and Conditions.

 

9.3 TIMELY NOMINATIONS

 

(a) Timely nominations are nominations submitted

consistent with the standard nomination cycle set out in Section 9.2(a).

 

(b) Nominations received after the timely nomination

deadline will be scheduled after the nominations received by that

deadline.