Canyon Creek Compression Company
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/01/1993, Docket: RS92- 57-003, Status: Effective
Original Sheet No. 117 Original Sheet No. 117 : Effective
GENERAL TERMS AND CONDITIONS
----------------------------
6. RECEIPT POINTS
6.1 FACILITIES AT RECEIPT POINTS
Unless otherwise agreed by Canyon, Canyon shall own,
operate and maintain all pipeline and measurement facilities
necessary to receive and measure gas hereunder. In the event any
such facilities are installed by Canyon, Section 8 of these General
Terms and Conditions shall apply.
6.2 OBLIGATION
Canyon's maximum obligation to receive gas at the
Receipt Point(s) under the Agreement shall never exceed the lesser
of: (a) the applicable MDQ under the Agreement in the aggregate or
at individual points, as specified in the Agreement or as applicable
at such point under this Tariff; or (b) the total daily volume
Shipper or its designee is able and willing to tender at the Receipt
Point(s).
6.3 LOCATION
Unless otherwise described in the Agreement, the Receipt
Point(s) for transportation Agreements shall be located at the
interconnection between the facilities of Shipper, or its designee,
and the facilities of Canyon.