GENERAL TERMS AND CONDITIONS
----------------------------
(5) To rectify imbalances or to conform physical flows to
nominations to the extent consistent with the specific Rate Schedule;
(6) To maintain System integrity;
(7) If there is a dispute over title, ownership or right
to tender or receive gas; or
(8) If capacity is required to provide a service with
higher priority.
(c) (1) If nominations under interruptible Agreements on any
day exceed Canyon's available capacity on that day to provide such services,
Canyon shall, to the extent possible given the priorities imposed by upstream
or downstream transporters, allocate available capacity as set out in this
subsection (c) among Shippers which have executed interruptible Agreements.
(i) Canyon shall schedule interruptible services
(including authorized overrun) based on the rate to be paid, from highest to
lowest daily rate, with service for which the highest daily rate being paid
is scheduled first. Any Shipper paying the maximum rate applicable to its
service (or revenue equal to or greater than the applicable maximum rate
pursuant to a Negotiated Rate or Negotiated Rate Formula) shall be afforded
highest priority even if a Shipper which has agreed to a Negotiated Rate or
Negotiated Rate Formula is paying a higher unit rate.
(ii) In the event there is insufficient capacity to
schedule all services for which the same rate is to be paid, Canyon shall
allocate the available capacity pro rata based on the confirmed nomination
volume.
(2) Notwithstanding Section 5.4(c)(1) hereof, Canyon
reserves the right, after a one (1) day notice, to interrupt service to any
interruptible Shipper paying a discount rate to enable Canyon to provide
service to another Shipper if such service would result in a higher unit
rate; provided, however, that Canyon will not interrupt service to a Shipper
paying the applicable maximum rate (or revenue equal to or greater than the
applicable maximum rate pursuant to a Negotiated Rate or Negotiated Rate
Formula) even if a Shipper which has agreed to a Negotiated Rate or a rate
under a Negotiated Rate Formula would pay a higher unit rate. Within such
one (1) day period, Shipper shall be allowed to increase its rate by any
amount up to the applicable maximum rate specified in this Tariff. A
Shipper agreeing to increase its rate hereunder shall be entitled to any
higher priority associated with such higher rate; provided, however,