Ozark Gas Transmission, L. L. C.

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/16/2009, Docket: RP09-1040-000, Status: Effective

First Revised Sheet No. 156 First Revised Sheet No. 156

Superseding: Sub Original Sheet No. 156

 

GENERAL TERMS AND CONDITIONS (continued)

 

(c) If Transporter reserves capacity for an expansion/extension

project, it will notify Shippers of its intent as part of

Transporter's posting of capacity on its Internet Website.

Transporter's posting for reserved capacity for future

expansion/extension projects shall include the following

information:

(1) a description of the project for which the capacity

will be reserved;

(2) the total quantity of capacity to be reserved;

(3) the location of the proposed reserved capacity on the

pipeline system;

(4) whether, and if so when, Transporter anticipates that

an open season for the capacity will be held or the

reserved capacity will otherwise be posted for bids;

(5) the projected in-service date of new facilities; and

(6) on an ongoing basis, how much of the reserved capacity

has been sold on a limited-term basis that would

otherwise be eligible for a right of first refusal.

 

The posting shall remain open for not less than five (5)

Business Days. Transporter will make reasonable efforts to

update the reservation posting up to the in-service date of

the project to reflect any material changes in the scope of

the project. If unsubscribed capacity that has been posted

for bid remains unsubscribed after posting, and if such

unsubscribed capacity is insufficient to serve the

expansion/extension project, the reservation posting or open

season will include a non-binding solicitation for turnback

capacity from Transporter's existing Shippers to serve the

expansion/extension project. Transporter shall post on the

Informational Postings area of its Internet Website a non-

binding solicitation for expansion project related turnback

capacity no later than 90 days after the close of an

expansion project's open season specifying the minimum term

for a response to the solicitation.

 

(d) If there are material differences between the terms and

conditions imposed on the expansion project open season and

the mandatory pre-reservation open season, Transporter shall

hold another open season for the available capacity that

uses the same terms and conditions used for the expansion

project open season. If the available capacity open season

is held subsequent to the expansion open season, Transporter

shall use the same terms and conditions used in the

expansion open season.