17.4 Any monetary reimbursement due Transporter from Shipper pursuant

to this Section 17 shall be due and payable to Transporter prior

to Transporter's commencement of construction of facilities to be

constructed, unless otherwise agreed by Transporter, and within

ten (10) Days of receipt by Shipper of Transporter's invoice(s)

for same; provided, however, subject to Transporter's written

consent, such monetary reimbursement, plus carrying charges

thereon, may be amortized over a mutually agreeable period not to

exceed the primary contract term of any Service Agreement between

Transporter and Shipper. Carrying charges shall be computed

utilizing interest factors acceptable to both Transporter and

Shipper. Unless Transporter and Shipper otherwise agree on

interest factors for computing the carrying charges for new

facilities, the interest rates determined by the Commission under

Section 154.501(d) of the Commission's regulations shall apply.

 

17.5 Reservation of Capacity For Expansion/Extension Projects.

 

(a) Transporter may elect to reserve for a future

expansion/extension project any unsubscribed or unallocated

capacity or capacity under expiring or terminating Service

Agreements where such capacity is not subject to a right of

first refusal or Shipper does not exercise its right of

first refusal to retain the capacity. Transporter may only

reserve capacity for a future expansion/extension project

for which an open season has been or will be held within one

(1) year of the date that Transporter posts such capacity as

being reserved. Prior to reserving capacity for an

expansion/extension project, such available capacity shall

have been posted on the Informational Postings area of

Transporter's Internet Website for at least five (5)

Business Days. Capacity shall be awarded or allocated in

accordance with the terms of the open season or this FERC

Gas Tariff.

 

(b) Capacity may be reserved for expansion/extension projects

only for a 12-month period prior to Transporter filing for

certificate approval for construction or acquisition of

proposed expansion/extension facilities, and thereafter

until all expansion/extension facilities related to the

certificate filing are placed into service by Transporter.