Ozark Gas Transmission, L. L. C.
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/16/2009, Docket: RP09-1040-000, Status: Effective
First Revised Sheet No. 155 First Revised Sheet No. 155
Superseding: Original Sheet No. 155
GENERAL TERMS AND CONDITIONS (continued)
17.4 Any monetary reimbursement due Transporter from Shipper pursuant
to this Section 17 shall be due and payable to Transporter prior
to Transporter's commencement of construction of facilities to be
constructed, unless otherwise agreed by Transporter, and within
ten (10) Days of receipt by Shipper of Transporter's invoice(s)
for same; provided, however, subject to Transporter's written
consent, such monetary reimbursement, plus carrying charges
thereon, may be amortized over a mutually agreeable period not to
exceed the primary contract term of any Service Agreement between
Transporter and Shipper. Carrying charges shall be computed
utilizing interest factors acceptable to both Transporter and
Shipper. Unless Transporter and Shipper otherwise agree on
interest factors for computing the carrying charges for new
facilities, the interest rates determined by the Commission under
Section 154.501(d) of the Commission's regulations shall apply.
17.5 Reservation of Capacity For Expansion/Extension Projects.
(a) Transporter may elect to reserve for a future
expansion/extension project any unsubscribed or unallocated
capacity or capacity under expiring or terminating Service
Agreements where such capacity is not subject to a right of
first refusal or Shipper does not exercise its right of
first refusal to retain the capacity. Transporter may only
reserve capacity for a future expansion/extension project
for which an open season has been or will be held within one
(1) year of the date that Transporter posts such capacity as
being reserved. Prior to reserving capacity for an
expansion/extension project, such available capacity shall
have been posted on the Informational Postings area of
Transporter's Internet Website for at least five (5)
Business Days. Capacity shall be awarded or allocated in
accordance with the terms of the open season or this FERC
Gas Tariff.
(b) Capacity may be reserved for expansion/extension projects
only for a 12-month period prior to Transporter filing for
certificate approval for construction or acquisition of
proposed expansion/extension facilities, and thereafter
until all expansion/extension facilities related to the
certificate filing are placed into service by Transporter.