Ozark Gas Transmission, L. L. C.
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/16/2009, Docket: RP09-1040-000, Status: Effective
First Revised Sheet No. 138 First Revised Sheet No. 138
Superseding: Original Sheet No. 138
GENERAL TERMS AND CONDITIONS (continued)
14.4 In the event there is more than one best bid and no Prearranged
Shipper has provided timely notice of an intent to match the best
bids, Transporter will offer the capacity subject to the release
in sequence to the bidders based on the time the best bids were
submitted with the capacity first offered to the bidder that
submitted a best bid first in time, until all capacity is awarded,
unless the Releasing Shipper specified a different tie-breaking
method in its offer to release capacity. In the event that more
than one best bid was submitted at the same time, Transporter will
offer available capacity to such bidders pro rata based on the
quantity specified in such best bids.
14.5 All potential Replacement Shippers that desire to bid on released
transportation capacity must pre-qualify with Transporter by (i)
submitting the information required in a valid Request for Service
submitted pursuant to Section 18 of these General Terms and
Conditions, (ii) demonstrating Creditworthiness in the same manner
and subject to the same standards and procedures as required for
Shippers under Section 30 of these General Terms and Conditions,
and (iii) executing, via the LINK® System, a Capacity Release
Umbrella Agreement in the form contained in this FERC Gas Tariff.
Once the conditions of this Tariff are met and the terms and
conditions specified in the Replacement Shipper's offer to release
are met, the Replacement Shipper will then be considered as any
other Shipper on Transporter's system. Any such Replacement
Shipper must comply with all provisions of this FERC Gas Tariff.