Ozark Gas Transmission, L. L. C.

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/16/2009, Docket: RP09-1040-000, Status: Effective

First Revised Sheet No. 36 First Revised Sheet No. 36

Superseding: Original Sheet No. 36

 

RATE SCHEDULE FTS (continued)

 

4. POINTS OF RECEIPT AND DELIVERY

 

4.1 Point(s) of Receipt. The Primary Receipt Point(s) for a Shipper's

FTS Agreement under this Rate Schedule FTS shall be at such points

as may be agreed to by the parties as set forth in executed FTS

Agreements between Transporter and Shipper and authorized by FERC

where Shipper shall deliver, or cause to be delivered, Natural Gas

to Transporter for transportation service. Shipper shall have the

right to request Point(s) of Receipt as Primary Receipt Point(s),

subject to Transporter's determination that it has adequate

available receipt capacity at such Point(s) of Receipt. If

Shipper requests a single Primary Receipt Point, Shipper's entire

MDQ will be allocated to such Primary Receipt Point as the MDRO.

If Shipper requests more than one Point of Receipt as a Primary

Receipt Point, Shipper shall also identify the portion of its MDQ

to be allocated to each Primary Receipt Point as the MDRO;

provided that the total of such MDRO must equal Shipper's MDQ.

Shipper may use any Point(s) of Receipt as a Secondary Receipt

Point(s) if such Point(s) of Receipt is not designated as Primary

Receipt Point(s) on Shipper's FTS Agreement, or to the extent

nominations for a Day at a Primary Receipt Point exceed the MDRO

for such point.

 

4.2 Point(s) of Delivery. The Primary Delivery Point(s) under this

Rate Schedule FTS shall be the points where Transporter shall

deliver Natural Gas to or for the account of Shipper after

transportation and shall be at such points as may be agreed to by

the parties as set forth in executed FTS Agreements between

Transporter and Shipper and authorized by FERC. Shipper shall

have the right to request Point(s) of Delivery as Primary Delivery

Point(s), subject to Transporter's determination that it has

adequate available delivery capacity at such Point(s) of Delivery.

If Shipper requests a single Primary Delivery Point, Shipper's

entire MDQ will be allocated to such Primary Delivery Point as the

MDDO. If Shipper requests more than one Point of Delivery as a

Primary Delivery Point, Shipper shall also identify the portion of

its MDQ to be allocated to each Primary Delivery Point as the

MDDO; provided that the total of such MDDO must equal Shipper's

MDQ. Shipper may use any Point(s) of Delivery as a Secondary

Delivery Point(s) if such Point(s) of Delivery is not designated

as Primary Delivery Point(s) on Shipper's FTS Agreement, or to the

extent nominations for a Day at a Primary Delivery Point exceed

the MDDO for such point.