Ozark Gas Transmission, L. L. C.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/1998, Docket: CP98-266-005, Status: Effective
Substitute Original Sheet No. 79 Substitute Original Sheet No. 79 : Effective
GENERAL TERMS AND CONDITIONS (continued)
6.4 Payment. Shipper shall pay Transporter at its general
office in Oklahoma City, Oklahoma, or at such other
address as Transporter shall designate in writing, by no
later than the tenth Day following receipt of the invoice
from Transporter, the amount due for the preceding Month.
Transporter will apply parties' payment per the support
documentation provided by the Shipper. The Shipper shall
indicate the invoice number on all payments.
6.5 Remedies for Nonpayment. Should Shipper fail to pay all
of the amount of any invoice as herein provided when such
amount is due, Transporter may charge interest on the
unpaid portion of the invoice computed from the due date
until the date of payment at the same rate of interest
and in the same manner as prescribed for pipeline refunds
as set forth in Section 154.501 of the Federal Energy
Regulatory Commission's Regulations under the Natural Gas
Act. If such failure to pay continues for thirty (30)
Days after payment is due, and Transporter has provided
Shipper and the FERC with at least ten (10) Days notice
that service will terminate due to the non-payment,
Transporter, in addition to any other remedy it may have
under an executed Service Agreement, may, after
application to and authorization by the FERC, if such
authorization is necessary, terminate the Service
Agreement.
6.6 Disputed Invoices. Shipper may dispute the amount of any
invoice or parts thereof due to a good faith allegation
of a billing error, made in writing to Transporter, with
supporting documentation, and pay to Transporter only
such amounts as it concedes to be correct if, within
thirty (30) Days of a demand made by Transporter, Shipper
furnishes a good and sufficient surety bond guaranteeing
payment to Transporter of the amount ultimately found due
upon such invoices after a final determination, which may
be reached either by agreement or judgment of the courts
as may be the case. If Shipper furnishes such a bond,
Transporter shall not be entitled to suspend further
delivery of Natural Gas unless and until default be made
in the conditions of such bond. No payment by Shipper of
the amount of a disputed invoice shall prejudice the
right of Shipper to claim that an adjustment of the
disputed invoice is required.
6.7 Adjustment of Billing Errors. If, subject to the time
limits set forth in this Section 6.7, it shall be found
that Shipper has been overcharged or undercharged in any
form