Young Gas Storage Company, Ltd.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/1999, Docket: RP99-359-000, Status: Effective
First Revised Sheet No. 119I First Revised Sheet No. 119I : Superseded
Superseding: Original Sheet No. 119I
FORM OF STORAGE SERVICE AGREEMENT
APPLICABLE TO RATE SCHEDULE IS-1
(Continued)
Shown below in tabular format is a representation this GISB Standard 1.3.2(ii),
(iii), and (iv). All times are in Central Clock Time.
Evening Intraday 1 Intraday 2
Cycle Cycle Cycle
(for flow on (for flow on (for flow on
next Gas Day) current Gas Day) current Gas Day)
(Interruptible (Interruptible
Nominations are Nominations are
subject to Bumping) subject to Bumping)
(i) Gas Day affected by Intraday
Nomination begins ------ 9:00 a.m. 9:00 a.m.
(ii) Intraday Nomination Period Ends
(Nominations leave control
of Nominating Party) 6:00 p.m. 10:00 a.m. 5:00 p.m.
(iii) Nominations received by
Transporter 6:15 p.m. 10:15 a.m. 5:15 p.m.
(iv) Transporter Quick Response
to Nominating Party 6:30 p.m. 10:30 a.m. 5:30 p.m.
(EDI Only)
(v) Completion of Upstream and
Downstream Interconnect
Confirmations 9:00 p.m. 1:00 p.m. 8:00 p.m.
(vi) Issuance/Posting of
Transporter's Report
of Confirmed Quantities
and Notices to Bumped
Parties 10:00 p.m. 2:00 p.m. 9:00 p.m.
(vii) Gas Day Affected by
Intraday Nomination begins 9:00 a.m. ------ -------
(viii) Nomination Effective Time 9:00 a.m. 5:00 p.m. 9:00 p.m.
(Grid-wide synchronization
Times, (GISB Standard
1.3.41)