Young Gas Storage Company, Ltd.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/1999, Docket: RP99-359-000, Status: Effective
Fourth Revised Sheet No. 119C Fourth Revised Sheet No. 119C : Superseded
Superseding: Sub Third Revised Sheet No. 119C
FORM OF STORAGE SERVICE AGREEMENT
APPLICABLE TO RATE SCHEDULE IS-1
(Continued)
provider from the service requester, the service
provider should then process the begin date/time and
end date/time consistent with the intentions of the
Standard 1.3.7 and then process the rest of the
transaction's data elements consistent with the
applicable standards to determine the business
results. When data is not supplied (e.g., is not
applicable, is not supported, or is not mutually
agreed upon), the pertinent portion of the key would
be determined to be null. (GISB Standard 1.3.27)
(iv) Nominations must specify a Begin and End Date. Such
dates must be no earlier than the effective date or
no later than the termination date of the service
agreement. Each Day, all Nominations for the next Day
which have been received by Young at or prior to the
Nomination Deadline shall be processed pursuant to
Article 5 of the General Terms and Conditions of
Young's Tariff.
(v) All Nominations, including intraday Nominations,
should be based on a daily quantity; thus, an
intraday Nominator need not submit an hourly
Nomination. Intraday Nominations should include an
effective date and time. The interconnected parties
should agree on the hourly flows of the intraday
Nomination, if not otherwise addressed in
transporter's contract or Tariff. (GISB Standard
1.3.9)
(c) Determination of Nomination Scheduling Cycle and reservation
of capacity.
(i) Transportation Service Providers should determine the
applicable Nomination processing cycle based upon the
receipt time and beginning effective Day of the
Nomination. Where Transportation Service Providers
support the processing of beginning effective time,