Young Gas Storage Company, Ltd.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2010, Docket: RP10-921-000, Status: Effective
Sixth Revised Sheet No. 77 Sixth Revised Sheet No. 77
Superseding: Fifth Revised Sheet No. 77
GENERAL TERMS AND CONDITIONS
(Continued)
6.2(g) (Continued)
(iii) With respect to the processing of requests for
decreases during the Intraday Nomination/Confirmation
process, in the absence of agreement to the contrary,
the lesser of the Confirmation Quantities should be the
new Confirmed Quantity, but in any event no less than
the elapsed-prorated-Scheduled Quantity. If there is no
response to a Request For Confirmation or an
unsolicited Confirmation Response, the greater of the
Confirmation Quantity or the elapsed-prorated-Scheduled
Quantity should be the new Confirmed Quantity.
(h) With respect to 6.2(g), if there is no response to a request
for Confirmation or an unsolicited Confirmation response,
Transporter should provide the Shipper with the following
information to explain why the Nomination failed as applicable:
(i) Transporter did not conduct the Confirmation;
(ii) the Shipper is told by Transporter that the upstream
Confirming Party did not conduct the Confirmation;
(iii) the Shipper is told by Transporter that the upstream
Service Requester did not have the Gas or submit the
Nomination;
(iv) the Shipper is told by Transporter that the downstream
Confirming Party did not conduct the Confirmation;
(v) the Shipper is told by Transporter that the downstream
Service Requester did not have the market or submit the
Nomination.
This information should be imparted to the Service Requester on
the Scheduled Quantity document. (NAESB Standard 1.3.22(iv))