Western Gas Interstate Company
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1993, Docket: RS92- 53-003, Status: Effective
Revised Original Sheet No. 205 Revised Original Sheet No. 205 : Superseded
RATE SCHEDULE IT-DN
INTERRUPTIBLE TRANSPORTATION SERVICE - DEL NORTE DIVISION
(continued)
Curtailment Over-Run Penalty, as defined in Section
15.5 of the General Terms & Conditions, applicable to
Shipper during the applicable Billing Month.
(e) Incidental Charges: Shipper shall reimburse Western
for any incidental charges incurred by Western in
providing this service. Such charges may include
filing fees and, subject to agreement and approval of
Shipper, costs of construction or acquisition of new
facilities necessary to render service or such other
charges as may be authorized by any regulatory agency
having jurisdiction.
5.4 For purposes of Section 5.3(e), the term "new facilities"
is defined as facilities required for Western to either
receive or deliver gas under this Rate Schedule and which
facilities are not existing on the date Shipper executes an
IT-DN Service Agreement for service hereunder. Section
5.3(e) pertains to facilities at receipt and delivery
points only. It is not intended to limit which party may
own, operate, install, or pay for facilities upstream of a
receipt point or downstream of a delivery point.
(a) New facilities may be installed by either Western or
Shipper as follows:
(1) Western will install, at its own expense, any new
facilities which, based on Western's estimates,
will generate annual revenues equal to or greater
than the annual cost of service associated with
such facilities. Revenues will be based on
projected annual incremental volumes of
throughput and peak usage for each year for the
depreciable life of the facilities to be built or
for the number of years under the initial term of
the operable service agreement, whichever is
shorter, and the currently effective rate for the