Jackson Prairie

Gas Storage Project Agreement

 

Certificated Characteristics and Capabilities

 

Characteristics and Capabilities of the Jackson Prairie Storage Project for

the 2008-2009 Storage Cycle and thereafter:*

 

Project Cushion Gas Requirement Not less than 20,969,646 Mcf

 

Zone 2 Not less than 16,969,646 Mcf

 

Zone 9 Not less than 4,000,000 Mcf

 

Project Working Gas Capacity Not more than 22,604,463 Mcf

 

Zone 2 Not more than 21,604,463 Mcf

 

Zone 9 Not more than 1,000,000 Mcf

 

Project Gas Capacity Not more than 43,574,108 Mcf

 

Zone 2 Not more than 38,574,108 Mcf

 

Zone 9 Not more than 5,000,000 Mcf

 

Project Firm Withdrawal Deliverability Not more than 850,000 Mcf Daily

 

Project Best Efforts Deliverability Not more than 150,000 Mcf Daily

 

 

* In addition to the stated quantities, the certificated Characteristics and

Capabilities of the Jackson Prairie Storage Project include any portions of

the expanded cushion and working gas capacities developed, month to month,

during the current water withdrawal/gas injection cycle of the Capacity

Expansion Project described in Exhibit G.