Puget Sound Energy, Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/22/2007, Docket: RP07-462-000, Status: Effective
Original Sheet No. 129 Original Sheet No. 129 : Effective
Exhibit C
(revised May 16, 2007 pursuant to Amendment No. 8)
to the
Jackson Prairie
Gas Storage Project Agreement
Certificated Characteristics and Capabilities
Characteristics and Capabilities of the Jackson Prairie Storage Project for
the 2007-2008 Storage Cycle and thereafter:*
Project Cushion Gas Requirement Not less than 20,561,732 Mcf
Zone 2 Not less than 16,561,732 Mcf
Zone 9 Not less than 4,000,000 Mcf
Project Working Gas Capacity Not more than 21,992,591 Mcf
Zone 2 Not more than 20,992,591 Mcf
Zone 9 Not more than 1,000,000 Mcf
Project Gas Capacity Not more than 42,554,323 Mcf
Zone 2 Not more than 37,554,323 Mcf
Zone 9 Not more than 5,000,000 Mcf
Project Firm Withdrawal Deliverability Not more than 850,000 Mcf Daily
Project Best Efforts Deliverability Not more than 150,000 Mcf Daily
* In addition to the stated quantities, the certificated Characteristics and
Capabilities of the Jackson Prairie Storage Project include any portions of
the expanded cushion and working gas capacities developed, month to month,
during the current water withdrawal/gas injection cycle of the Capacity
Expansion Project described in Exhibit G.